Timeline

November 11, 2015

Our Land

The land we bought was measured.

January 16, 2016

The first building

The house we bought in Blora was disassembled and loaded onto the truck and send to Karimunjawa Island.

January 21, 2016

The Staff House

The construction team started to clear the bushes in the area. When the land was cleared, a ceremony for success was celebrated. After that, the construction team could begin with the foundation and to rebuild the staff house. The construction team has achieved a lot in a short time. Many thanks to the worker.

February 1, 2016

Construction of the groundwater well

The construction team started with the construction of the groundwater well. At first, it went very well, then came a layer of clay, which was a good sign of groundwater. Until they hit a big stone. They started smashing the stone but had to stop the project after heavy rain. At the next opportunity, the construction team will continue with additional tools.

June 2, 2016

Construction of the toilet and Mandi
Our construction workers started building the WC and the Indonesian toilet (Mandi) for the staff house. From now on we can live in the rebuilt staff house. It will be the basis for our workers.

June 2, 2016

Construction of the septic tank

The construction team started to build two septic tanks for our warehouse.

June 6, 2016

Way to the beach

A second construction team paved a path through the terrain from the upper to the lower Ground.

June 17, 2016

The Groundwater Well Part two

One of our most important pillars for our resort was finished. The Well was dug by hand and without any machinery. A masterpiece of craftsmanship. The well will provide us with water for showering and washing.

November 9, 2017

Clearing the Terrain

The loggers began to cut the trees and bushes around the road for expansion.

November 10, 2017

The road enlargement

The first path was extended to a road with an excavator.

November 9, 2017

Interior construction of the staff house
In the staff house, the reconstruction of the interior's was started. It was built a guest room and a family room to sleep. The living room also got a new outfit.

November 11, 2017
Levelling the Ground
The heavy construction machines began to level the property.

September 9, 2018
The construction of the dive center

The work was started with 8 construction workers. They did everything with their bare hands, without machines all craftsmanship. Only for concreting the ceiling was prepared with a concrete mixer. You deserve a big compliment and thank you.

June 16, 2019

The opening ceremony

After several years of planning and construction, the Dive Center was officially opened. The guests were introduced to our team and the Dive Center. After the ceremony, successful talks and relationships with the residents and business people of Karimunjawa took place.

November 20, 2021

The respected old Jawa house has been renovated.

Before that, all materials and a lot of groceries were bought. Everything was brought from Kudus to Karimunjawa in three vehicles. First, a ceremony for success was held. Then the workers began to dismantle the roof and the wooden walls, some of which had been damaged by termites. Bees had made their home in the partition walls. The main honeycombs were relocated into a hollow tree trunk. The roof structure was replaced with an aluminum frame. The back walls were rebuilt with cement blocks. In addition to the main house, a storage space and a magazine were built. On the other side of the building, the washing facility has been renewed with a cement floor and a new roof.

December 11, 2021

The diving center gets a concrete road

After a ceremony with the neighbors and construction workers for the success of the construction project, work started the next day with full enthusiasm. First, the road to the beach was built. A jetty over the sea will later be built there. In the second stage, workers began building the cross street to the west side of the property. A rainwater canal was built at every street to drain the property. In the third part, the road was built from the lower crossing to the upper main road. The driveway has also been extended so that we can later create a beautiful structure at the entrance to the diving center.

February 6, 2022
The diving center gets a monument.
Our designer and artist Baim Masto has created an impressive work of art. The monument was all made by hand. It is a beautiful work of art that reflects our dive center.
Many thanks to Baim Masto, Mas Sabar & all the workers who helped.

March 11, 2022
The diving center gets a monument.

The back of the monument is also finished.

What a unique artist!!!

We are so proud of you

Baim Toto Masto

February 6, 2022
The restaurant building is being renovated.
The temporary restaurant has been expanded and renovated. It now has a refrigerated food storage room, a new larger kitchen, and a dining area. The interior was designed by Baim Parnoto and made by our own carpenter. Thank you to everyone who helped create this beautiful building.

June 6, 2022
The jetty.

After a ceremony for success of the construction of the jetty, the first foundation pole was set. The local fishermen built the jetty with diligence and precision. Thanks to the fishermen and those who helped build this phenomenal jetty.

August 16, 2022

The new Warehouse.
A new multipurpose building with laundry, staff, and a storage room was built. So that we can store our equipment, materials, and laundry. The additional staff room is for a future member of management.

July 23, 2023
The Greenhouse.

A new resource for our resort. In the future, we can grow our own lettuce and vegetables. Fresh from the garden onto the table.

September 17, 2023
Dive boat Kemujan Divers II
Our captain Mr. Safak and boat builder has built a new dive boat for us. The boat was built according to our own ideas and requirements. It is a unique boat that will serve us well.